Milestones
A Milestone is a dated window of delivery: a goal description, an optional start and target-end date, an ordered list of named phases with one marked current, and a set of issues. It’s the layer above issues — where an issue says what, a Milestone says what the team is collectively driving toward right now, and how close it is.
A Milestone is not a sprint. There’s no fixed cadence, no velocity tracking, no burndown chart, and no automatic carry-over of unfinished work. A Milestone spans however long its goal needs — weeks to months — and is closed by hand when the work is done or abandoned.
An issue belongs to at most one Milestone. Multiple Milestones run at once; a Milestone is owned by at most one Team.
Creating a Milestone
Section titled “Creating a Milestone”From a project’s Board, open the milestone list in the left sidebar and choose New. Fill in:
- a title;
- a description (markdown) — the goal of this window of work;
- a status:
Draft,Active,Completed,Archived, orCanceled; - an optional start date and target end date;
- an owning team (optional, but required before the Milestone can become Active — the “Milestone needs a team” guardrail);
- phases — an ordered list of named stages, e.g. development → feature freeze → code freeze → deployment, each with an optional target date.
On create, an AI assistant pane sits to the left of the form: describe the Milestone in your own words and it fills in the fields for you to review. It proposes; nothing is created until you click Create.
Phases
Section titled “Phases”A Milestone holds a single current phase, which the team advances by hand as work moves through it — there’s no date-driven auto-advance. The board’s milestone overview and the milestone’s own phase rail both render from it. Issues attach to the Milestone as a whole, not to a phase.
Progress
Section titled “Progress”Milestone progress is an issue count: complete issues ÷ all issues that aren’t canceled, inside that Milestone. Every issue counts the same regardless of its own task breakdown.
Working a Milestone on the board
Section titled “Working a Milestone on the board”The project Board is scoped to one Milestone at a time: pick it from the
left-hand list and the columns show that Milestone’s issues, except
Backlog, which is always the project-wide pool of issues that aren’t in
any Milestone yet. Drag a card out of Backlog to assign it to the selected
Milestone; drag one in to return it to the pool. A Board · List · Timeline
toggle switches the same view between the kanban columns, a flat list, and a
project-wide timeline across every Milestone.
Associating a Backlog issue with a Milestone that has an owning Team stamps the issue’s team to match, unless the issue already has one — and promotes the issue to Planned, since it’s now planned work.
Health
Section titled “Health”A Milestone carries a computed health — see the Status page for the four signals behind it. There’s no posted status update to weigh against it: a Milestone’s displayed health is always the computed one.